From: Richard Kahn Sent: Saturday, December 22, 2018 1:14 PM To: Jeffrey Epstein Subject: Fwd: Status Update for LSJ Pump Station and GSJ Containerized plant HBRK Associates Inc. 575 Lexington Avenue, 4th Floor New York NY 10022 =egin forwarded message: From: < Date: December 22, 2018=at 8:09:40 AM EST To: "'brice gordon'" Cc: "michael lid=en" Subject: Status Update for LSJ Pump Station an= GSJ Containerized plant —R=chard Kahn"' Brice: As of close of business yesterday, here is were everyth=ng stands on the two ongoing projects: LSJ Pump Station<=b> 1. The basket strainers arrived yesterday, ther= were the last items we were waiting on to finalize the system fabrication.=o:p> 2. The equipment is scheduled to ship to Tropical on Janua=y 3rd. We will coordinate shipping with Daphne once we hav= made final arrangements. 3. Assuming the equipment arrive= late the following week, we would propose coming to St. Thomas the week of=January 14th to install the pump station equipment, install the n=w seal for the cartridge filter housing, replace the pH probes and associat=d wiring and update the controls for the new configuration. I underst=nd the fiber optic cable has been shipped from AVL. When do you antic=pate having it installed so we can finalize the new controls? This wi=l drive the equipment installation schedule. EFTA_R1_01802526 EFTA02608983
GSJ 25K Plant 1. The container will be completed late=next week and ship to us on January 3rd or 4th. =/o:p> 2. Installation of the equipment will take approximately 3 week= which puts shipment sometime during the week of January 28th with installa=ion probably the week of 11 February. 3. On your end, have=you decided on the routing of the feedwater and brine disposal pipelines?&n=sp; There will also need to be 208 three phase power at the seawater pumpin= station as well as one control conduit from the pump station to the RO pla=t. There will also need to be control conduits from the two cisterns t= the RO plant as well as the interconnecting piping (1.5 to 2" diam=ter is recommended). =/o:p> Our facility is closed next week through Ja=uary 2nd. If you need any technical support, I am availabl=. Hope you and the staff have a great holiday season and I look forwa=d to working with you to complete the water upgrades on both of your island=. Dean Bedford PE Gemin= Seawater Systems LLC 8916 SW 44<=up>th Lane 2 EFTA_R1_01802527 EFTA02608984