oject. phase One - Design 1. Schematic Design. Based on the approved Conceptual Design and Client's authorization to proceed, Gensler will develop the Schematic Design, consisting of: a) Site plan; b) Building elevations; c) Typical building sections; d) Floor plans; e) Outline description of building systems
t. James Pool Area and Screening Room Agreement for Architectural Services September 18, 2009 Page 3 2. Design Development. Based on the approved Schematic Design and Client's authorization to proceed, Gensler will proceed with Design Development, to further develop the design, including: a) Site plan; b) Building ele
oject. phase One - Design 1. Schematic Design. Based on the approved Conceptual Design and Client's authorization to proceed, Gensler will develop the Schematic Design, consisting of: a) Site plan; b) Building elevations; c) Typical building sections; d) Floor plans; e) Outline description of building systems
t. James Pool Area and Screening Room Agreement for Architectural Services September 18, 2009 Page 3 2. Design Development. Based on the approved Schematic Design and Client's authorization to proceed, Gensler will proceed with Design Development, to further develop the design, including: a) Site plan; b) Building ele
oject. Phase One - Design 1. Schematic Design. Based on the approved Conceptual Design and Client's authorization to proceed, Gensler will develop the Schematic Design, consisting of: a) Site plan; b) Building elevations; c) Typical building sections; d) Floor plans; e) Outline description of building systems
t. James Pool Area and Screening Room Agreement for Architectural Services September 18, 2009 Page 3 2. Design Development. Based on the approved Schematic Design and Client's authorization to proceed, Gensler will proceed with Design Development, to further develop the design, including: a) Site plan; b) Building ele
Entities connected to both the Schematic Design and Schematic Design and Client

Jeffrey Epstein
PERSONConstruction Administration
ORGANIZATIONStandard Terms and Conditions
ORGANIZATIONSubstantial Completion
ORGANIZATIONEpstein Interests
ORGANIZATIONHBRK Associates
ORGANIZATIONGensler
PERSONProduct Data
ORGANIZATIONBasic and Additional Services
ORGANIZATIONStructural Engineering
ORGANIZATIONCivil Engineering
ORGANIZATIONReimbursable
PERSONBulletins
PERSONFire Alarm
PERSONReview Submittals
PERSONWarwick Ian Wicksman
PERSONAndrew P. Cohen
PERSONRobert Jernigan
PERSONTom Sze
PERSON
Prince Andrew
PERSON