PROGRESS THIS WEEK Task Goal for week of 07.27.09 Status at end of week of 07.27.09 Goal for week of 08.03.09 Construction Item - Office 1. Office Stonework Completed Type B window, pointing 90% complete. Complete stonework. 2. Archive Area interior — Casework and trim package Pricing received, sh