EFTA00715903
4. No crew provided for installation. 5. LSJ responsible for the cement work, footings and bolt installation prior to the arrival of the building. Buck Steel - I. Florida company. 2. Sixty day manufacturing time for the shed. 3. $42,790 for the building quoted (40' by 60'). EFTA00715903 4. (5) man cr
EFTA00721424
m: Daphne Wallace To: "Jeffrey E." <[email protected]> Subject: Re: Date: Mon, 13 Apr 2015 15:58:39 +0000 Greetings Sir, Yes, that crew did. Buck Steel outsources the erection portion of the project. You do not wish to use them for the fabrication portion? Respectfully, Daphne On Mon, Apr 13, 2015
EFTA00804948
Blue Water Construction Bids (BWC) LSJ ChiIlex Window $ 54,258.75 Lead time 8 to 10 Weeks LSJ RO Shed BWC $ 268,509.94 10 Weeks, 10 Guys Buck Steel $ 83,640.00 Lead time10 Weeks HVAC TBA LSJ Clearing Cost TBA GSJ GSJ Q Hut 45 $ 93,663.75 4-5 Weeks 5 Guys GSJ Q Hut 25 $ 52,710.00 4 We
EFTA00859792
ds is currently working on detail drawings for the garages over the RO and Mechanical buildings for your review. He has also contacted a fabricator, Buck Steel. John plans to have the drawings to you this week. Do you wish to see him? Lucas has one person in mind for you, if you were still interested. Dir
EFTA00859783
ds is currently working on detail drawings for the garages over the RO and Mechanical buildings for your review. He has also contacted a fabricator, Buck Steel. John plans to have the drawings to you this week. Do you wish to see him? Lucas has one person in mind for you, if you were still interested. Dir
EFTA00859797
f they are but careful re people that beed to put up On Mon, Apr 13, 2015 at 11:58 AM, Daphne Wallace < wrote: Greetings Sir, Yes, that crew did. Buck Steel outsources the erection portion of the project. You do not wish to use them for the fabrication portion? Respectfully, Daphne On Mon, Apr 13, 2015
EFTA00602832
00.00 36,000.00 IMPORTANT NOTES - PLEASE READ • This quote is based on Buck Steers interpretation of plans and/or conversations with the customer. Buck Steel is NOT responsible for any errors and/or ommissions. • Carefully check this quote for completeness and verify the accuracy of the information conta
EFTA00612596
CING & PAYMENT TERMS The project will be undertaken at a price of $9,9rn.00 for labor and materials with the exception of the sheds. The sheds from Buck Steel will be purchased by Little St James who will also Day for all shipoina costs from factory to iob site. Scope Of Work I Labor Price GENERAL REQUI
EFTA00626934
LSJ to view job. David would also look at finishing Chillax Window job and Flashing on Great Room At this time I am awaiting updated proposals from Buck Steel for Sheds and Expert Builders for foundation work both vendors have indicated I should receive today !!! please advise regards Brice On Mon, Jan
EFTA00705547
LSJ to view job. David would also look at finishing Chillax Window job and Flashing on Great Room At this time I am awaiting updated proposals from Buck Steel for Sheds and Expert Builders for foundation work both vendors have indicated I should receive today !!! please advise EFTA00705549 regards Bric
EFTA00522041
site, Construction crew ETA 1/11 -JE approved layout for extra metal sections & roller doors to old engineering area. Drawings/photos forwarded to Buck Steel, will finalize this - Installation of new bolts — complete 22. Eauioment/Household Purchase and Delivery - (1) 2012 JCB 8035Z Mini Excavator with
EFTA00522069
site, Construction crew ETA 1/11 -JE approved layout for extra metal sections & roller doors to old engineering area. Drawings/photos forwarded to Buck Steel, will follow up this week - Installation of new bolts — 80% complete 25. Equipment/Household Purchase and Delivery - (3) Terex RL-4000 6kW Light T
EFTA00522072
s of 9/21) 25. Main compound - Projector Screen — new limit switches and motor required — Danny completed repairs 9/20 - COMPLETE 26. Steel shed — Buck Steel (FL) — JE approved mock-up 9/26, changes 9/27 — Buck Steel working on the final specs and quote 27. Equipment to be Purchased - (1) light generato
EFTA00522081
Cecile 10/25 — there is an issue with the site possibly being in a flood zone. Reviewing with Jaredian Design Group (John Woods). 23. Steel shed — Buck Steel drawings on site. Shed ordered, will schedule removal of existing bolts patterns and installation of new 24. Equipment Purchased - (3) Terex RL-40
EFTA00522075
outfall down the slope from the pad — architect will send updated plans once the pipe is added — to submit to DPNR for permitting 24. Steel shed — Buck Steel sent out drawings to STT via UPS on 10/12 25. Equipment to be Purchased - (1) Light generator, (2) arms with lights to be hard wired - quote receiv
EFTA00522083
ey forwarded to the architect 9/18 - he will complete the plan by 10/5, submit to DPNR for permitting (Cecile's update as of 9/21) 24. Steel shed — Buck Steel — JE approved mock-up 9/26, changes 9/27 — Buck Steel working on the final specs/quote 25. Equipment to be Purchased - (3) light generators — Larry
EFTA00522078
ey forwarded to the architect 9/18 - he will complete the plan by 10/5, submit to DPNR for permitting (Cecile's update as of 9/21) 24. Steel shed — Buck Steel — JE approved mock-up 9/26, changes 9/27 — Buck Steel working on the final specs/quote 25. Equipment to be Purchased - (1) light generator, (2) arm
EFTA00556192
outfall down the slope from the pad — architect will send updated plans once the pipe is added — to submit to DPNR for permitting 24. Steel shed — Buck Steel sent out drawings to STT via UPS on 10/12 25. Equipment to be Purchased - (1) Light generator, (2) arms with lights to be hard wired - quote receiv
EFTA00556405
Cecile 10/25 — there is an issue with the site possibly being in a flood zone. Reviewing with Jaredian Design Group (John Woods). 23. Steel shed — Buck Steel drawings on site. JE requested that American Steel cost out the price for a new shed also requesting cost of removal of existing bolt pattern & epox
EFTA00693139
from EB which was for Only Part of the Workshops, Not RO Building and had no relationship to drawings 1/17/17 Both Set of Drawings where forward to Buck Steel to bid for Metal Sheds for RO and Mechanical/Workshops 1/17/17 Drawings sent to EB for them to review there bid for complete job 1/27/17 Drawings

Jeffrey Epstein
PersonAmerican sex offender and financier (1953–2019)

Marc Rich
PersonAmerican commodities trader (1934–2013)

Condoleezza Rice
PersonAmerican diplomat and political scientist (born 1954)

Richard Kahn
PersonJeffrey Epstein's accountant and estate co-executor (2005-present)
John P. Woods
PersonPerson referenced in documents

Oliver Stone
PersonAmerican film director, screenwriter, and producer (born 1946)
Daphne Wallace
PersonJeffrey Epstein's property manager and associate; managed Little St James island operations; named in Epstein's will
Leon Black
PersonAmerican billionaire businessman (born 1951)
Landscaping
PersonNER artifact: Common word misidentified as person name
Richard Barnett
PersonIndividual referenced in Epstein documents
John Deere
PersonPerson referenced in documents
Gerry & TJ
OrganizationOrganization referenced in documents
Darren Indyke
PersonAmerican lawyer, longtime personal attorney and co-executor of Jeffrey Epstein's estate
Black Heli
LocationLocation referenced in documents
COMPLETE - JE
OrganizationOrganization referenced in documents
Cecile de Jongh
PersonFormer First Lady of the U.S. Virgin Islands, managed Epstein's USVI-based companies
Mechanical Building Transformer
OrganizationOrganization referenced in documents

Samantha Power
PersonIrish-American academic, author and diplomat
RO & Generators
OrganizationOrganization referenced in documents
Nanny Cay
LocationLocation referenced in documents