From: Richard Kahn Sent: Friday, March 16, 2018 7:04 PM To: Jeffrey E. Subject: Hardwood Flooring project update reminder to advise brice on which door openings you would =ike enclosed for Cabannas 1, 2 & 3 this will =eed to be done before coral stone tiles are removed which is now =entatively scheduled for April 2nd Wood Floor project for Cabanas (4), =ym, Chillax and Master will begin April 16th and be completed by May =1st Final =ricing for Wood Floors came to $220,000 - i will send 50% deposit today ts requested by Absolute Flooring i was able to lower price by $9,300 and = added scope as that they will now be performing leveling of subfloors =hich was originally omitted in scope and =robably another $7,500 in savings additional costs for project are =hipping container - estimated -> 5,000 airfare,=food and hotels for 3-4 men for 45 days =/span> -> 25,000 Total Projected Cost =50,000 Richard Kahn HBRK Associates Inc 1 EFTA_R1_01630605 EFTA02502350