From: Richard Kahn < Sent: Tuesday, May 1, 2018 1:34 PM To: Jeffrey E. Subject: brian bates not sure how happy you were with brian bates work however he =as already exceeded 25 days brice projected for GSJ tiki house and =eawater shed.. i reached out to jay this =m to review his findings during walk thur of islands and next =teps.. Richard Kahn HBRK Associates Inc. Begin forwarded message: From: =/b>Richard Kahn ‹ > Subject: =/b>Re: =SJE_BB_1099_043018 Date: =/b>April 30, 2018 at 8:05:49 PM =DT To: Cc: = not sure on 1099 =owever regardless he is responsible for picking up income i noticed he has billed 8100 =hich is 27 days vs projected total of 25 or 7,500 total labor for both =rojects can you please update me status of his =rojects thank you Richard Kahn HBRK =ssociates Inc. EFTA_R1_01552871 EFTA02452437
On Apr 30, 2018, at 8:01 PM, LSJ GSJ wrote: Good =vening Rich Brian asked would he be getting a 1099 for =is work on I.S1 and GSJ? Please advise Thank =ou 2 EFTA_R1_01552872 EFTA02452438