To: Schoettle[ JEE 'eevacation mail.com]; Brice Gordon ; Emad Hann From: curtis Sent: Tue 6/9/2009 1:22:32 PM Subject: Master Bath & Bed Title: Mastcr Bath & Bed Doug • April 4th - CZM permit start up was required— exterior demolition and plant clearing, silt fencing. • April 27th — 28th Master Bathroom taken apart — during inventory of Bedroom/Bathroom • Sinks outside for no good reason — but they are undamaged and will be properly stored. • We can begin - Master bath foundation, walls, electrical and plumbing roughing when you give us the go ahead, Building Permit received last week. • Exterior column design unclear. • Details & specifications based on exactly what you had before — we can complete most issues with this information — No Designer on Board. • We can reused — Vanities which are in fine shape — shower doors to speed schedule forward • Need budget approval to allocate funds — order long lead On 6/9/09 8:05 AM, "JEE" <[email protected]> wrote: when was my master bathrroom taken apart„ why are the sinks outside for weeks on end ? when was the cabana taken down„ when is the master bath project actually going to begin„ EFTA_R1_01518905 EFTA02443511