To: Lesley Gro Cc: Anna Rodri Glidden From: Sent Subject Daphne Wall Stephanie Remington Thur 5/23/2019 6:29:58 PM Re: Punchlist #52 - LSJ MC Kitchen Kick Plate Mike I would say maybe two weeks out to start, then two weeks to finish (MC Kitchen, FPP Kitchen, Tiki Kitchen - in that order) Stephanie Remington LSJE, LLC On Thu, 23 May 2019 at 13:59, Lesley Groff wrote: ok. thank you So realistically, kick plates beginning of next week? or when? considering the new request? ( , Stephanie Remington wrote: We have 2 carpenters on tiki tile and two carpenters installing 5 Palms windows. The windows should be complete tomorrow, but JE sent instruction today to also build a door and some panels at 5 Palms. Once complete, will shift to Kickplates. On Thu, May 23, 2019 at 1:41 PM Lesley Groff wrote: Since this is a priority for Jeffrey, Can we please get an update today on kick plate and installation. ..I'm not sure who is heading this task. My notes say it should be finished with `in house' carpenters... (Rich, this is directed toward LSJ managers...just replying to your mail to keep the flow!) On May 22, 2019, at 2:35 PM, Richard Kahn wrote: this is a priority for jee can you please advise when work will begin and be completed and then update on smart sheet thank you Richard Kahn HBRK Associates Inc. 575 Lexington Avenue, 4th Floor EFTA_R1_01112256 EFTA02286208
New York, NY 10022 IIIII Stephanie Remington LSJE, LLC EFTA_R1_01112257 EFTA02286209