ZORRO DEVELOPMENT 1/21/14 Satellite: Deposit paid to Advanced Comm — 1/17 Meeting with Advancced Comm 1/23 to confirm network map & scope of work. References/Updated Proposal from SpaceNet & Jim Cloud forwarded to Rich — 1/20 Meeting today with RMC Electric to confirm poles for links to MH & RC Pool Reulaster/SDa Clean: attached photos Plaster work finished, acid wash & filling started today Bead Blasting of Spa Tile, unsucessful, have requested estimate to replace tile & grout will forward once in hand Gate: Project Complete as of 1/21 Sony: Issues with Tablet not communicating with equipment. New Tablet has been ordered incase it is a Tablet issue IR to be extended closer to seating area. Installer back on site 1/23 to resolve issues Installation of moulding on hold until all issues are resolved Dakota Well: Rig was due on site today, delayed due to an emergency call out. Now due 1/23 Cactus Removal: attached photos Fabrication of railway tracks for drags complete. Removal of cactus continues as weather allows EFTA_R1_0200381 3 EFTA02684213