From: Larry Visoski < Sent: Thursday, April 20, 2017 4:02 PM To: Je vacation; Rich Kahn Subject: Nautica update Attachments: IMG_1201.1PG; Untitled attachment 00238.txt; IMG_1198JPG; Untitled attachment 00241.txt; IMG_1197JPG; Untitled attachment 00244.txt; IMG_1202.1PG; Untitled attachment 00247.txt; IMG_1203JPG; Untitled attachment 00250.txt Jeffrey Raining in Fla„ can't paint today,. -Interior side panels are primed and ready for High gloss paint,. -raised side walk Way is ready for paint„ -mid seat with 2" angle is ready for install„ -raised rear bench seat back is ready to install,. -metal shop fabricating hand rails Shop estimate till completion 3 weeks,. I'll say, 4 weeks,. Ready to ship to LSJ Thx Larry Raised side ledge ready for paint 1 EFTA_R1_01417052 EFTA02391194