From: Jermaine Rua Sent: Tuesday, September 2, 2014 9:07 PM To: Jeffrey Epstein Subject: Tower Project Status Good day =oss, As per our conversation, here is the proposed schedule =or completion of the tower project : * ./span>lf the second payment ($ 90,019.85 ) is =pproved and received this week the order can be made 9/8/14. From =here: o 3 Weeks for balance =f the equipment to arrive o 1 Week to complete =SJ installation o 1 Week to complete =TC installation o 2 Weeks to finalize =11 sites including programming and active swaps for =ackup. =o:p> Does Terrence have permission =o work on adjusting the tower to the height of the berm this week =tarting tomorrow 9/3, while you are in residence? Regards JRuan 1 EFTA_R1_01408530 EFTA02387283