Epstein Residence New Generator Budget for Construction 1/20/2009 Generator Work Budget Amount Supervision & General Conditions S 3,500 Worth Builders Proj. Mgmt. Fee 1,000 Structural Engineering & Geotechnical Work 2,200 Electrical Engineering & Architects Work 4,000 Electrical Work, Equipment & Machinery 68,000 Garage Floor/Driveway Cutting & Repairs 3,000 Generator Foundation & Mounting Slab 3,200 Screen Walls (if needed) MC Removal & Replacement of Landscaping NIC Contingency for unknowns 3,000 Plumbing Work for New Gas Line 3,500 Subtotal 91.400 Permits 2,742 Contractor's Overhead and Profit @10% 11,297 General Liability Insurance @1% 1.054 Budget Total $ 106,493 Notes: 1. Owner is responsible for ARCOM Approval costs, if not a staff approval 2. Owner is responsible for meter costs, if gas meter needs to be upgraded in size 3 Screen walls around the generator on 3 sides may be required by Code Local architect to determine this & help with ARCOM approvals 4. This is a Time and Material Budget--Cost plus 10%+1% This not a Guaranteed Maximum Contract Proposal. 5. Energy Efficient Electric Proposal is attached for your information & review. ' d Lipeag wted sJapting q4Jom e9b:L.0 CO SI 4414 EFTA00728708