Andrew Levy- Design Assistant 19 Pinecliff Road Chappaqua, NY. 10514 Hasan-Uddin Khan 143 Concord Avenue Lexington, Massachusetts 02421, USA Project Title: LSJ Time Sheet #3 3/3/09 - 3/25/09 Week 8 Date Description Hours 3/3/09 Meeting, create scheme 11 plan 4 3/4/09 Meeting, scheme 11 massing, roof plan 5 3/5/09 finish scheme, Send, prepare drawing sets, 6 3/6/09- 3/9/09 Site analysis on location 8 Weekly Total 23 Week 9 Date Description Hours 3/10/09 Meeting, gather info, organize site photos 5 3/11/09 Meeting, begin scheme 12, Massing study with photos 6 3/12/09 Meeting with Bradford Associates + develop site scheme 8 3/13/09- scheme 12 plan with site, scheme 12 level 0, new vestibules 8 Weekly Total 27 EFTA00724703
Week 10 Date Description Hours 3/16/O9 Create sections -NS, EW, study proportions, study grade levels 6 3/17/09 scheme 12 plan, (bedroom, changing, level 0) 6 3/18/09 scheme 12 Plan, site levels, view axis, look at entry 8 3/19/09 Massing model with new graded contours, adjust plan 8 3/20/09 Coordinate and finalize drawing, send email package 8 Weekly Total 36 Week 11 Date Description Hours 3/23/09 Meeting, new plan, new massing 8 3/24/09 Meeting w/ Bradford assoc.+ continue plan/massing 8 3/25/09 plan, massing, coordinate site plan with BA- Send 8 Weekly Total 24 Total Hours 110 EFTA00724704