From: Leighton Allenby To: Jeffrey Epstein Cc: Anna Rodriquez , NYC - Richard Kahn LSJ - Danny Vicars Leighton Allenby Subject: Updated timeline for LSJ - August 11, 2015 Date: Wed, 12 Aug 2
ard Kahn LSJ - Danny Vicars Leighton Allenby Subject: Updated timeline for LSJ - August 11, 2015 Date: Wed, 12 Aug 2015 01:54:37 +0000 Hello Mr. Epstein, Please review updated timeline below. Cabana 1 & 2 1. Stone work and grout/mud completed today by Omar 2. Install shower heads and valves on Wed
arate email to follow I believe everything was covered. Best, Leighton Leighton Allenby Director of Pro erties On Tue, Aug 11, 2015 at 8:42 AM, jeffrey E. < > wrote: send me an upadated punchlist please with proposed finish dates. master , cabana etc. please note The information contained in this comm
From: Leighton Allenby To: Jeffrey Epstein Cc: Anna Rodriquez , NYC - Richard Kahn
015 Date: Wed, 12 Aug 2015 01:54:37 +0000 Hello Mr. Epstein, Please review updated timeline below. Cabana 1
clean carpets on Thursday 4. Install new pads for rug, install rug and bed - Friday AM 5. Clean entire cabana 1 & 2 on Friday AM to afternoon Mr. Epstein Bedroom floor 1. Pokey is laying floor, then sanding and finishing 2. Last coat of finish by 26th 3. Put room back together 28th and clean entire building
this list does't overwhelm Anna and Danny. Let me know. Best, Leighton Leighton Allenby Director of Pro erties On Tue, Aug 18, 2015 at 6:17 PM, jeffrey E. <[email protected]> wrote: One week ago if next time i can have a spread sheet , or an annotatd punch .. all the better. for example, ice maker w
YC - Richard Kahn < >, Leighton Allenby < Subject: Re: Updated timeline for LSJ - August 11, 2015 Date: Wed, 19 Aug 2015 17:34:14 +0000 Hello Mr. Epstein, I reviewed the LSJ punch list at length today with Rich. Anna and I will make the corrections and update by tomorrow afternoon. I will also work o
From: Leighton Allenby To: "Jeffrey E." <[email protected]> Cc: NYC - Richard Ka
015 Date: Wed, 19 Aug 2015 17:34:14 +0000 Hello Mr. Epstein, I reviewed the LSJ punch list at length today w
clean carpets on Thursday 4. Install new pads for rug, install rug and bed - Friday AM 5. Clean entire cabana 1 & 2 on Friday AM to afternoon Mr. Epstein Bedroom floor 1. Pokey is laying floor, then sanding and finishing 2. Last coat of finish by 26th 3. Put room back together 28th and clean entire building
arate email to follow I believe everything was covered. Best, Leighton Leighton Allenby Director of Properties On Tue, Aug 11, 2015 at 8:42 AM, jeffrey E. <[email protected]> wrote: send me an upadated punchlist please with proposed finish dates. master , cabana etc. please note The information con
sty lights at pool eating area? i dont know what hangar door motor means/. On Tue, Aug 11, 2015 at 7:54 PM, Leighton Allenby 5 > wrote: Hello Mr. Epstein, Please review updated timeline below. Cabana 1 & 2 I. Stone work and grout/mud completed today by Omar 2. Install shower heads and valves on Wed
From: "Jeffrey E." <[email protected]> To: Leighton Allenby
5 at 7:54 PM, Leighton Allenby 5 > wrote: Hello Mr. Epstein, Please review updated timeline below. Cabana 1
clean carpets on Thursday 4. Install new pads for rug, install rug and bed - Friday AM 5. Clean entire cabana 1 & 2 on Friday AM to afternoon Mr. Epstein Bedroom floor I. Pokey is laying floor, then sanding and finishing 2. Last coat of finish by 26th 3. Put room back together 28th and clean entire building
arate email to follow I believe everything was covered. Best, Leighton Leighton Allenby Director of Pro erties On Tue, Aug 11, 2015 at 8:42 AM, jeffrey E. <[email protected]> wrote: send me an upadated punchlist please with proposed finish dates. master , cabana etc. please note The information con
rusty lights at pool eating area? i dont know what hangar door motor means/. On Tue, Aug 11, 2015 at 7:54 PM, Leighton Allenby > wrote: Hello Mr. Epstein, Please review updated timeline below. Cabana 1 & 2 I. Stone work and grout/mud completed today by Omar 2. Install shower heads and valves on Wed
From: "Jeffrey E." <[email protected]> To: Richard Kahn Su
015 at 7:54 PM, Leighton Allenby > wrote: Hello Mr. Epstein, Please review updated timeline below. Cabana 1
clean carpets on Thursday 4. Install new pads for rug, install rug and bed - Friday AM 5. Clean entire cabana 1 & 2 on Friday AM to afternoon Mr. Epstein Bedroom floor I. Pokey is laying floor, then sanding and finishing 2. Last coat of finish by 26th 3. Put room back together 28th and clean entire building
Entities connected to both Jeffrey Epstein and Epstein Bedroom

Richard Kahn
PERSONJermaine Ruan
PERSON
Oliver Stone
PERSONBoscoe
ORGANIZATIONHydro
ORGANIZATIONCabana 1 & 2
ORGANIZATIONElectrician
PERSONDanny V & Danny E
ORGANIZATIONCabana 2 & 3
ORGANIZATIONWaterfall Project
LOCATIONI. Stone
ORGANIZATIONI. Pokey
ORGANIZATION