ization costs, if we Newman & Moll for future work. Or We can reconcile the concrete by deducting $20,500 off this budget now and let them finish. Curtis EFTA_R1_00202387 EFTA01827299
d to show latest cost revisions based on adjustments both up and down in individual line items showing present cost down by $317,858.67. NOTES: 1. Newman & Moll will complete their contracted work in less than a month. 2. The contract was bought out for $689,000, leaving $20,500 remaining in the budget. (see
Paid to date - 379,669.60 THIS PAYMENT - 134,442.80 BALANCE TO FINISH 174,857.60 They will be pouring concrete roof of mechanical in two weeks. Curtis wrote: EFTA_R1_00204713 EFTA01829024
frey Epstein Sent Tue 4/14/2009 8:13:31 PM Subject: Re: Concrete approval ok On Tue, Apr 14, 2009 at 3:20 PM, curtis R Jeffrey - please approve Newman & Moll concrete requisition #5 for $ 134,442.80 Contract - 689,000.00 Paid to date - 379,669.60 THIS PAYMENT - 134,442.80 BALANCE TO FINISH 174,857.
rey - please approve Newman & Moll concrete requisition t5 for $ 134,442.80 Contract - Paid to date THIS PAYMENT BALANCE TO FINISH They will be Curtis 689,000.00 379,669.60 134,442.80 174,857.60 pouring concrete roof of mechanical in two weeks. EFTA_R1_01474623 EFTA02412861
To: From: Sent: Subject: JEE[[email protected]] curtis R Tue 4/14/2009 7:20:37 PM Concrete approval Jeffrey - please approve Newman & Moll concrete requisition t5 for $ 134,442.80 Contract - Paid to date THIS PAYMENT BALANCE TO FINISH They will be Curtis 689,000.00 379,669.60 13
h the next phase, whichwe will present to you later this week, as I mentioned below. Please review this existing budget presented for your approval Curtis Original approved budget: $2,330,543.72 Revised budget: $2,012,685.05 PAID to DATE: $940,413.62 On 4/17/09 4:33 PM, "JEE" <[email protected]
d to date Please find attached revised Original approved budget — same as I sent you last Friday — with Paid to date as per yesterday and including Newman & Moll which you approved and will be posted today. Note : we are still carrying $709,500 in their Budget line item rather than their buy out number of 68
ization costs, if we Newman & Moll for future work. Or We can reconcile the concrete by deducting $20,500 off this budget now and let them finish. Curtis EFTA_R1_01516848 EFTA02442071
d to show latest cost revisions based on adjustments both up and down in individual line items showing present cost down by $317,858.67. NOTES: 1. Newman & Moll will complete their contracted work in less than a month. 2. The contract was bought out for $689,000, leaving $20,500 remaining in the budget. (see
Entities connected to both Curtis and Newman & Moll

Jeffrey Epstein
PERSONBrice Gordon
PERSON
Green
PERSONRevised Mechanical Building Budget
ORGANIZATIONThe Original Budget
ORGANIZATIONB. Keep Newman & Moll
ORGANIZATION